Project Profile
Value: US$100 million
Location: 25 miles southwest of the Opal Hub in Uinta County, Wyoming
Production: 12,000 barrels per day of oil and 83 MMcfd of gas
Start-up Year: 2013
Serendah will be developed using an integrated oil and gas production and accommodation platform to be tied back to a pipeline linking the Merapuh platform to the Golok riser platform. The Serendah platform is expected to process 12,000 barrels per day of oil and 83 MMcfd of gas. Serendah is a marginal oil and gas field about 16.5 kilometres northeast of the Golok gas platform. Production at Serendah was targeted to start up in the fourth quarter of 2013.
Operator:
Murphy Sarawak Oil Co. Ltd.: Operator with 85% interest
Petronas: 15% interest
Contractors:
Aker Solutions: Supply 24 sets of splitter wellhead systems
Brooke Dockyard and Engineering Works Corporation
Boustead Penang Shipyard: Provide engineering, procurement, construction and commissioning of Belum Topsides
Hercules Offshore: Drilling development well
Kencana: EPC for Serampang-A (SEPA) Production of Topside Facilities for Phase 1 SK-309/311
Tanjung Offshore Services
TH Heavy Engineering Bhd: EPCC contract