Project Profile
Value: US$297 million
Location: Bombay High, Mumbai
Start-up Month and Year: April 2012
Upstream condensate reserves: 8 million boe
Upstream Oil Reserves: 18 million bbl
Upstream Gas Reserves: 231 billion ft³
The B-22 project includes the B-22, BS12, BS13 and B149 discoveries, as well as an oil rim in Bassein gas field. The facilities will include a B-22A 9-slot wellhead-cum-process platform; two wellhead platforms – BS-13A (and B-149A, along with modification of two platforms (BB and BF). There will also be a 56.5 km of submarine pipelines and drilling of 16 wells. There is an estimated production cap of 18 million barrels of oil, 8.2 million barrels of condensate and 231 billion cubic of gas by 2019-20.
Operator:
ONGC (Oil and Natural Gas Corporation)
Contractors:
National Petroleum Construction Co (NPCC): EPC contract
Punj Lloyd: EPC for the installation of 122 kilometre subsea pipeline