Oil&Gas
Kepodang oil & Gas Field
2017-12-21 15:00  点击:1
VIP:1级

Project Profile


Value: US$350 million
Location: Off Indonesia
Water Depth: 65 metres
Start-up Year: 2012

The Kepodang project will have a central processing platform, a tripod wellhead platform during phase one, with wellhead platforms to follow in the following phase. The project also includes construction of an onshore gas receiving terminal. One of the other packages will include infield lines and a 205 km 14-in trunkline from the Kepodang field to Semarang of Central Java. A water depth is on average 65 metres of water. The additional satellite wellhead tower at area D will be tied back to the production platform located at area A of the reservoir. Four production wells are to be drilled, with two on area D and one well each on area A and C, where a wellhead tower will be installed under phase 1.


Operator:

Petronas Carigali Sdn Bhd: Operator with 100% interest


Contractors:

Bakrie & Brothers: Pipeline network construction

McDermott International: Procurement, construction, installation and commissioning of a 5,802-tonne central processing platform


Sub contractor:

PT IKM Indonesia: Project management, provision of labor, equipment and consumables