Value: Undisclosed
Location: western Niger Delta, Nigeria
Capacity: 70,000 barrels of crude oil per day
Area: unknown
Start-up Year: 2016
The Dibi Long-Term project is designed to rebuild the Dibi facilities that were vandalized in 2003 and replace the existing Early Production System facility placed in service in 2007. The facilities have a maximum production capacity of 70,000 barrels of crude oil per day. A final investment decision was reached in the first quarter of 2013 and start-up is expected in 2016. Chevron Nigeria is the operator of the project.
Operators:
Chevron Corp (Nigeria): Operator with 100% interest
Contractors:
IMRA Group: Contract to supply 33 experienced specialists which were covering almost 40 % of the entire crew onboard. Among the supplied personnel are Electrical Engineer, Mechanical Engineer, Operations Manager, Piping Engineer, Sr. Instrument Technician, Production Supervisor, Sr. Mechanical Supervisor, Production Engineer, etc.
McGrath Power Solutions Ltd: Facility maintenance works
KYJE GEODRILL SERVICES LIMITED: Soil Investigation for Dibi Long Term Facility