Basic Info:

Nord Stream (former names: North Transgas and North European Gas Pipeline; Russian: Северный поток, Severny potok) is an offshore natural gas pipeline from Vyborg in the Russian Federation to Greifswald in Germany that is owned and operated by Nord Stream AG. The project includes two parallel lines. The first line was laid by May 2011 and was inaugurated on 8 November 2011. The second line was laid in 2011–2012 and was inaugurated on 8 October 2012. At 1,222 kilometres (759 mi) in length, it is the longest sub-sea pipeline in the world, surpassing the Langeled pipeline. It has an annual capacity of 55 billion cubic metres (1.9 trillion cubic feet), but its capacity is planned to be doubled to 110 billion cubic metres (3.9 trillion cubic feet) by 2019, by laying two additional lines. Due to EU restrictions on Gazprom, only 22.5 billion cubic metres (790 billion cubic feet) of its capacity is actually used. The name occasionally has a wider meaning, including the feeding onshore pipeline in the Russian Federation, and further connections in Western Europe.

       Shareholders:

Gazprom(51%), Wintershall(15.5%), E.ON(15.5) , N.V. Gasunie(9%), ENGIE (9%)

Tech Info:

Russian onshore pipeline

Main article: Gryazovets–Vyborg gas pipeline

Construction of the feeding pipeline in Russia (Gryazovets–Vyborg gas pipeline) began on 9 December 2005 in the town of Babayevo in Vologda Oblast. It was completed in 2010. This pipeline is operated solely by Gazprom. It is a part of the integrated gas transport network of Russia connecting existing grid in Gryazovets with the coastal compressor station at Vyborg.The length of this pipeline is 917 kilometres (570 mi), the diameter of the pipe is 1,420 millimetres (56 in), and working pressure is 100 standard atmospheres (10 MPa), which is secured by six compressor stations. The Gryazovets-Vyborg pipeline, parallel to the branch of the Northern Lights pipeline, also supplies gas to the Northwestern region of Russia (Saint Petersburg and Leningrad Oblast). A branch pipeline in Karelia will connect this feeding pipeline with Finland.

Western European pipelines

Main articles: OPAL pipeline and NEL pipeline

The Western European part of the project includes two transmission pipelines in Germany. The southern pipeline (OPAL pipeline) runs from Greifswald to Olbernhau near German-Czech border. It connects Nord Stream with JAGAL (connected to the Yamal-Europe pipeline), and STEGAL (connected to the Russian gas transport route via Czech and Slovak republics) transmission pipelines. The Gazelle pipeline, put into operation in January 2013, links the OPAL pipeline with South-German gas network.

The western pipeline (NEL pipeline) runs from Greifswald to Achim, where it is connected with the Rehden-Hamburg gas pipeline.Together with the MIDAL pipeline it creates the Greifswald–Bunde connection. Further gas delivery to the United Kingdom are made through the connection between Bunde and Den Helder, and from there through the offshore interconnector Balgzand–Bacton

Gazprom has also bought an abandoned mine (Hinrichshagen Structure) in Waren, which is planned to convert into the largest underground gas storage in Europe with capacity of 5 billion cubic metres (180 billion cubic feet).

Contract:

Work preliminary front-end engineering was done by Intec Engineering. The design engineering of the subsea pipeline was done by Snamprogetti (now part of Saipem) and the pipeline was constructed by Saipem. Saipem gave sub-contract to Allseas for laying more than 1/4 of both the pipelines. The seabed was prepared for the laying of the pipeline by a joint venture of Royal Boskalis Westminster and Tideway. The pipes were provided by EUROPIPE, OMK, and Sumitomo. Concrete weight coating and logistics services were provided by EUPEC PipeCoatings S.A. For the concrete weight coating new coating plants were constructed in Mukran (Germany) and Kotka (Finland).[19] Rolls-Royce plc supplied eight industrial aeroderivative gas turbines driving centrifugal compressors for front-end gas boosting at the Vyborg (Portovaya) gas compressor station.  Dresser-Rand Group supplied DATUM compressors and Siirtec Nigi SPA provided a gas treatment unit for the Portovaya station.

For the construction period, Nord Stream AG created a logistic center in Gotland. Other interim stock yards are located in Mukran, in Kotka, in Hanko (Finland) and in Karlskrona (Sweden).

 

 

 