Tombua-Landana Project
2017-12-21 15:00  点击:0
VIP:1级

Project Profile


Value: US$3.8 billion
Location: 80km offshore Angola in West Africa
Recoverable resources: 350 million barrels
Start-up Year: September 2009
Water Depth: 1,200 ft

The Tombua-Landana project covers the development of the Tombua and Landana fields, which are situated 80km offshore Angola in West Africa. The project lies at a water depth of 1,200ft in the eastern section of block 14. Chevron is the operator of the field with a 31% interest. Partners include Sonangol (20%), Eni (20%), Total (20%) and Galp Energia (9%). The field came onstream in September 2009 and was developed with an investment of US$3.8bn. The Tombua field was discovered in 1997 by the Tombua-1 well. The Landana field was discovered in 2001 by the 14-6X / 6XST-1 well. The Tombua-Landana reservoirs are of the Lower Miocene CN3 age and are made of high-quality sands deposited in a series of structural and stratigraphic traps. The fields are estimated to contain recoverable resources of 350 million barrels.

In June 2006, first oil was achieved from the Landana North-1 subsea well, which was connected to the Benguela Belize-Lobito Tomboco (BBLT) compliant piled tower (CPT). The well was drilled to gather reservoir information and plan the development of the fields. A total of 11 reservoirs are to be developed as part of the project. Most of these reservoirs are at their bubble points, therefore, pressure maintenance is essential to ensure maximum recovery. The project received government approval in November 2006 and in 2007, pre-drilling activities at the fields began. A total of 46 wells were drilled and tied-back to the Tombua Landana CPT. A tender-assisted drilling (TAD) rig is moored near the production platform to carry out drilling operations. The project was designed to ensure zero gas flaring and zero discharge of produced water. The produced natural gas is processed and stored in an existing reservoir on block O until the Angola Liquefied Natural Gas project being built in Soyo is ready. The produced water is recycled and reinjected into the reservoirs.

KBR provided the front end engineering services for the Tombua-Landana project. The front end engineering design and project management services for the CPT were provided by Mustang Engineering. Daewoo Shipbuilding & Marine Engineering (DSME) was awarded a US$1.27bn contract for building the platform. DSME subcontracted Gulf Marine Fabricators for fabrication of the top and bottom sections of the CPT. Heerema Fabrication Group was responsible for the fabrication of the base structure and foundation piles of the CPT. The accommodation facility of the platform was manufactured by Delta Engineering. Sonamet was responsible for the manufacture and supply of the platform\'s drilling template. InterMoor was awarded the contract for providing a mobile offshore drilling unit to pre-drill the platform wells. Seadrill was contracted to supply the TAD rig in August 2006. Gusto MSC supplied telescopic gangways for the CPT. Fairstar Heavy Transport transported the topside modules of the platform. Subsea 7 was contracted for the supply and installation of tie-back facilities including manifolds, flowlines, jumpers and umbilicals. Vetco Gray supplied subsea equipment for the project, which included a tree system, manifolds, and well jumpers and production control systems. Acergy West Africa installed the oil and gas export pipeline.

Operators:

Chevron: Operator with 31% interest

Sonangol: 20% interest

Eni: 20% interest

Total: 20% interest

Galp Energia: 9% interest

Contractors:

Acergy West Africa: Installed the oil and gas export pipeline

Daewoo Shipbuilding & Marine Engineering (DSME): Building the platform

Delta Engineering: Manufactured accommodation facility of the platform

Fairstar Heavy Transport: Transported the topside modules of the platform

Gusto MSC: Supplied telescopic gangways for the CPT

Heerema Fabrication Group: Fabrication of the base structure and foundation piles of the CPT

InterMoor: Providing a mobile offshore drilling unit to pre-drill the platform wells

Mustang Engineering: The FEED and project management services for the CPT

KBR: FEED contract

Seadrill: Supply the TAD rig

Sonamet: Manufacture and supply of the platform\'s drilling template

Subsea 7: Supply and installation of tie-back facilities including manifolds, flowlines, jumpers and umbilicals

Vetco Gray: Supplied subsea equipment for the project, which included a tree system, manifolds, and well jumpers and production control systems

Sub contractors:

Gulf Marine Fabricators: Fabrication of the top and bottom sections of the CPT awarded by DSME