Project Profile
Value: Undisclosed
Location: from Cushing, Oklahoma, to oil tanks near Houston, U.S. Gulf Coast, USA
Length: unknown
Capacity: 450,000 barrel-per-day
Start-up Year: October 2014
Enbridge Inc\'s new 450,000 barrel-per-day Seaway Twin pipeline, to carry Canadian oil sands crude to North America\'s largest refining complex on the U.S. Gulf Coast, will likely start operating in October 2014. Enbridge’s pipeline is most likely to be filled with crude from the company\'s new 600,000 bpd Flanagan South pipeline. Seaway Twin will carry crude from Cushing, Oklahoma, to oil tanks near Houston, and although the pipeline was mechanically completed in early July, it will not start operating before Flanagan South, which will run from Illinois to Cushing, is finished in early October.
Operators:
Enbridge Inc: Operator with 100% interest