Project Profile
Location: From Green Canyon Block 860, approximately 200 miles southwest of New Orleans to an existing third-party pipeline system, Gulf of Mexico, USA
Water Depth: 5,300 feet
Length: 34 miles
Start-up Year: 2016
Enbridge Inc. will build, own and operate a crude oil pipeline in the Gulf of Mexico to connect the proposed Heidelberg development, operated by Anadarko Petroleum Corporation, to an existing third-party pipeline system. The lateral pipeline is expected to be operational by 2016. Construction of the pipeline is subject to finalisation of definitive agreements and sanction of the development by Anadarko and its project co-owners. The Heidelberg lateral will originate in Green Canyon Block 860, approximately 200 miles southwest of New Orleans and in 5,300 feet of water. The pipeline will be 20 inches in diameter and approximately 34 miles in length.
Operators:
Enbridge Inc.: Operator with 100% interest