Project Profile


Value: $3,500 Million
Startup Year: 2012
Water Depth: 1300m
Upstream Oil Reserves: 500
Location: Blocks 640, 641, 596, 597, Green Canyon, Gulf of Mexico

The Tahiti development consists of a floating production facility supported by a truss spar located in Green Canyon Block 641 in 4,000\' water depth, with two subsea drill centers: the Production Drill Center North (PN) located in Block 596, and the Production Drill Center South (PS) in Block 640 and a Discovery Well located in Block 640. Tahiti has reserves in the order of 400-500 mmboe, will be capable of producing 125,000 barrels of oil and 70 million cubic feet of gas per day. Will be put into production in two phases.

Topsides: 9950 tonne production module, 6500 tonne utility module, 2500 tonne module support frame, to be supported by 24,000 tonne spar hull about 170 metres long with diamater of 39 metres.

Pipeline: 55-mile, 24\" crude oil pipeline from Tahiti to Amberjack pipeline; capacity of 300,000 b/d.
First production expected mid-2008. Phase 1 cost $1.8B.

Phase II: Eight 15,000-psi subsea trees. Completion 2012.

Operators:

Chevron: Operator with 58% interest

Statoil: 25% interest

Total: 17% interest

Contractors:

Waldemar S. Nelson and Co. Inc.: Topsides

Mustang Engineering: Topsides FEED, detailed engineering, project management and procurement assistance to Chevron

Technip: Production topsides and hull for the spar, topsides fabrication at Gulf Marine Fabricators and hull fabrication in Finland. FEED and EPC for Truss Spar and Mooring Systems.

Gulf Marine Fabricators: Topsides fabrication

Cameron: Subsea systems

Amberjack Pipeline Company: Pipeline

Expro: Electro-hydraulic deep-water safety systems

J Ray McDermott: Pipeline installation

ClampOn

Consafe Engineering: DP accomodation and construction support vessel

Deepwater Specialists: Commissioning

Aker Solutions: Umbilicals

Subsea 7: Subsea installation

Insensys Oil & Gas (Schlumberger)

FloaTec (Floatation Technologies Inc): Buoyancy module

Subsea 7: Engineering and installation contract for Phase II

Sub Contractor:

Grenland Group: Sub contracted for Minox