Project Profile
Location: East of the Shaikan block, Kurdistan Region, Iraq
Capacity: 10,000 barrels of oil per day
Storage Capacity: 30,000 barrels
Start-up Year: March 2013
Construction and commissioning of an Extended Well Test facility (EWT) for the Bijell discovery has commenced by Gulf Keystone. The Bijell EWT facility will have a total gross capacity of 10,000 barrels of oil per day and a storage capacity of 30,000 barrels. The facility is scheduled to be completed in March 2013. The facility will be tied to the Bijell-1 discovery well, which will be completed as a producer once a work-over rig has arrived in late February 2013 with first test production expected in May 2013.
Operators:
Gulf Keystone: Operator with 100% interest