Project Profile
Value: US$150 million
Location: Al Basra, Iraq, to FAO depot (North of Arab Gulf) onshore pipeline
Start-up Year: -
The project consists of supply and execution & commissioning of a 18² x 0.438 gas pipeline, consisting of all coating & joining accessories, the proposal must cover all engineering, design details, supply of materials and construction from Zubair1 depot to FAO depot. The project is an EPC contract with inspection commissioning & start up acc.
Scope of work:
1) The work should include execution of a 10 metre width service road along the pipeline route.
2) Dredging of pipeline route should be acc. to design requirements.
3) Welding procedure and included work.
4) Side booms should be used for pipe lift & transport, a sand bed burring required under and above the pipeline.
5) Passing pipe through crossing with rivers, roads, railway underground pipes, cable, etc, to international standard.
6) Use of boring procedure for crossing with roads, railway cables to applicable stds.
7) Tie in works with Zubair one & FAO depots should be included.
8) Hydrostatic test to ASME std.
Operator:
South Oil Company: Operator with 100% interest
Third Party : Gadeer Baghdad Company
Contractor : CPECC
Sub-Contractor : MSK Group