Project Profile


(Additional Researched project Information)

Value: US$2,100 million
Location: Ruwais, Abu Dhabi, UAE
Start-up Year: Q3 2013

The project involves construction of an NGL recovery train to increase its present offshore gas production by 1 billion cu. ft/d of high pressure gas.

The IGD Project will be built at a new location in Habshan titled Habshan 5. There will be 4 Gas Processing Trains with total processing capacity of 2,000 MMSCFD. Of this, 1,000 Million Standard Cubic Feet Per day (MMSCFD) of Gas will be transported from Offshore field Umm Shaif via Das Island to enable ADMA-OPCO to meet their planned increase in Oil Production. The remaining 1,000 MMSCFD of Gas will comprise of a mix of Associated Gas as a result of increase in Oil Production by ADCO from 1.4 to 1.8 MM Barrels/day and Non-associated gases of high sourness from Habshan gas fields. The Habshan 5 complex will also build 4 new Sulphur Recovery Units with recovery efficiency upto 99.9%. It will reduce emission of toxic gases considerably meeting the environment standards of ADNOC.

Operator:

Abu Dhabi Gas Industries (GASCO): Operator with 100% interest

Contractors:

Flour Mideast Ltd: Pre-FEED and FEED contract

KBR Middle East: Overseeing FEED

EPC contract joint venture with:-

Petrofac Abu Dhabi
GS Engineering & Construction Company Ltd

WorleyParsons: Overseeing EPC

Sub Contractors:

Siemens LLC: Engineer and supply an integrated power solution

Target Engineering and Construction Company: Marine works