Project Profile
Value: US$560 million
Location: 80 km southeast of the Asab Field
Start-up Year: 2013
Qusawira is an undeveloped oil field, which is located about 80 km southeast of the Asab Field. The works to be carried out under Phase I will be limited to the southern block of the field, which contains the developing Thamama Zones A/B and F.
Under the terms of the agreement, NPCC will be responsible for the EPC of 350 km of pipelines, as well as production facilities including central and remote degassing stations, oil, water and gas injection wells, and additional associated works such as overhead transmission and fiber optic cables.
As part of the 1.8 MMbbl/d expansion scheme, ADCO is also planning to increase production at the existing Northeast Bab oil field and to commence production from three new oil fields, namely, the Bida Al Qemzan, Qusawira and Bab fields.
The overall project is scheduled for completion 33 months after the contract becomes effective.
Operators:
ADCO - 60% (operator)
BP - 10%
Total - 10%
CNPC - 8%
Inpex - 5%
CEFC China Energy - 4%
GS Energy - 3%
Contractors:
NPCC: EPC contract
Foster Wheeler: PMC contract
Subcontractors:
Consolidated Contractors Company: New central degassing station 30 KBOPD, new remote degassing station, 118km 4\" - 8\" produced oil flow lines, 9km 20\" transfer line, 7km 6\" gas transfer line, 64km 3\" gas injection lines, 80km 14\" main oil line, 2 new water injection clusters including 5 injection wells and 8km 6\" - 8\" flow lines, and 57 well tie-ins