Project Profile
Value: US$1.6 billion
Startup Year: 2015
Location: Al Wusta (OM) Block 15
The Saiwan East-3 has flowed at rates close to 11,000 barrels per day during production tests of the horizontal section drilled in the Khufai reservoir. The Khufai reservoir target was hit at 38 metres higher than in the Saiwan East-2 discovery well.
Operators:
CC Energy: Operator with 50% interest
Tethys Oil: 30% interest
Mitsui & Co.: 20% interest
Contractors:
KCA Deutag: Drilling contractor
Gaffney, Cline & Associates (GCA): Consultants