Bure Gas Field - Block 49/28
2017-12-21 15:00  点击:0
VIP:1级

Project Profile


Location: Southern Gas Basin, UK
Water depth: 35 m
Discovery year: May 1983
Start-up year: October 1986 (Bure O) and 1998 (Bure West PL1635)
Production cease: 2014

Bure gas field was developed via one subsea well connected to the Thames Complex. The producing wells are at Bure O (49/28-8) and Bure West (49/28-18). The reservoir is mainly aeolian dune sandstones of the Rotliegendes Leman Sandstone Formation.

The Thames Complex is comprised of three platforms: a wellhead AW, a reception AR and process AP. The AR platform separates gas prior to processing and exports via the Thames AW wellhead platform. Production ceased in 2014 and decommissioning plan was submitted on 16th October 2015.


Operators:


Perenco: Operator 23.33% interest

Tullow Oil (BP sale in 2000): 66.67% interest

Centrica: 10% interest