Project Profile


Value: US$97 million
Location: Barrow-in-Furness town, county of Cumbria, UK
Capacity: unknown
Area: unknown
Start-up Year: Q4 2015

Barrow Gas Terminal is situated in Barrow-in-Furness, Cumbria on the Irish Sea coast, UK. Costain has won a contract with Centrica Energy for the provision of Engineering Procurement and Construction (EPC) services as part of Centrica Energy’s Barrow Gas Terminals Project.

The Barrow Terminals Project represents a total investment of US$115 million by Centrica Energy. At Barrow, gas is processed from the North and South Morecambe and surrounding fields in the East Irish Sea.

The terminals project, which is scheduled to complete in Q4 2015, enables increased asset utilisation, provides compliance with future environmental requirements and supports field life extension within the East Irish Sea. Costain initially provided Centrica Energy with a Front End Engineering Design (FEED) review in relation to the project at the Barrow onshore terminals and is now looking forward to supporting the customer through to full onsite implementation.

Operators:

Centrica Energy: Operator with 100% interest

Contractors:

Costain: Contract with Centrica Energy for the provision of FEED and Engineering Procurement and Construction (EPC) services