Project Profile


The Isarene permit area is located in the south of the Illizi Basin in South Eastern Algeria. The area covers some 7,520 sq km (equivalent to about thirty North Sea blocks). The In Amenas project is located 120km north of Isarene.

The Isarene PSC covers Blocks 228 and 229a, and contains the Ain Tsila gas-condensate discovery. The Ain Tsila field is estimated to hold reserves of 2.1 trillion cubic feet of sales gas, 67 million barrels of condensate, and 108 million barrels of liquid petroleum gas (LPG). The gas condensate field was discovered in 2009, following the drilling of the Ain Tsila-1 well. Hydrocarbons in the Illizi Basin are located within Silurian shales found in Carboniferous and Devonian and Ordovician reservoirs, with the largest volumes found in the Ordovician reservoirs. The Isarene concession comprises three other prospects namely Isarene Nord-Est, Isarene Nord-Ouest and Hassi Tab Tab. 

Operators:

Groupment Isarene (joint operating group formed by the companies below)

PetroCeltic International: Operator with 38.25% interest

Sonatrach: 43.375% interest

ENEL: 18.375% interest


Contractors:

Petrofac: EPC contract (March 2019)

Dalma Energy LLC.: No. 12 200 horsepower drilling rig

Expro Group: Well services

G3Baxi Partnership: Field development conceptual studies

KCA Deutag: Drilling contractor

Ove Arup & Partners: Geotechnical studies

CB&I: Contract by Groupement Isarene to provide front end engineering and design (FEED) services for the Ain Tsila gas field development with CB&I's project scope including FEED development for a grassroots 420 million cubic feet per day gas plant facility, plus three associated pipelines and well collection

SINOPEC International Petroleum Service Corporation ("SINOPEC"): Contract for the provision of a drilling rig. The 1500 horse power rig, which is now built and ready to ship, will drill up to 24 new development wells.