Oil&Gas
Hachinohe LNG Terminal
2017-12-21 15:00  点击:8
VIP:1级

Project Profile


Value: US$558 million
Location: Port Island, Kawaragi District, Port of Hachinohe, Aomori, Japan
Processing capacity: 60,000 tons tons/annum
Vaporizers: 4 units with a capacity of 2tons per hour
Storage capacity: 4,500KL x 1 - 140,000KL x 2
Start-up Year: 2015

In March 2007 the Hachinohe LNG Satellite Terminal was completed. In 2010 the Operator, Nippon Oil decided to expand and build a new terminal in order to comply with the demand growth particularly in industrial sector and to expand the company\'s supply areas. In October 2010, JGC Corporation was appointed as EPC contractor for the project by the Operator. Construction works on the project were completed by 1Q 2015.

Operators:

Nippon Oil: 100% interest

Contractors:

JGC: Contracted to construct the terminal (2010)
联系方式